ERP Delivery

Paper Enterprises:
5 risks caught before go-live.

A Bronx distributor of food, janitorial and restaurant disposable products was moving off a legacy AS400 system while relocating its facility. Incipient Corp verified readiness across 11 modules, caught five critical risks before cutover, and order fulfillment kept running through the move.

142
Items verified across 11 modules
5
Critical risk categories caught before cutover
~34%
Lower five-year TCO on the Odoo 19 path
READINESS BEFORE CUTOVER 01 · GAP ANALYSIS 21 pages AS400 vs PBS comparison 60+ item scope register → 02 · READINESS 142 items 11 modules · 11 sessions 136 open items tracked → 03 · GO / NO-GO 5 risks caught Caught before cutover No order disruption FIVE CRITICAL RISK CATEGORIES Payment processing Routing Allocation override EDI / SPS Commerce E-Store
Industry
Wholesale distribution
Location
The Bronx, NY
Timeline
2025 to 2026
Stack
Odoo 19
The Challenge

A legacy system, a facility move, and no room for error.

Paper Enterprises Inc. distributes food-related, janitorial and restaurant disposable products from the Bronx. Sales, inventory, accounting, warehouse and transportation all ran on a legacy AS400 system, and the company was preparing to convert to a new distribution ERP.

Two things made that risky. Nobody had written down how the business actually operated, so there was no baseline to check a new system against. And the conversion was happening alongside a facility relocation, which meant any ERP-driven problem with orders would land on customers.

"What set Incipient apart was their willingness to get on-site and learn how our business actually operates."
Howard Cohen, VP Customer Relations, Paper Enterprises Inc.
What We Did

Verify everything before anyone flips the switch.

The engagement ran in two phases: document how the business really works, then check the new system against it, module by module, with the people who run each department. Incipient acted as project manager for the conversion and stayed on it through the go/no-go decision.

  • Phase 1: a 21-page, version-controlled gap analysis of the AS400 against PBS across Sales, Inventory and Accounting
  • Built a dependency matrix, a pain-points matrix, a RACI and a scope register of 60+ line items
  • Phase 2: a 142-item verification of the AS400 against the new ERP across 11 modules
  • Ran 11 on-site sessions with department heads, each ending in a written record of what was verified, pending or at risk
  • Validated financial processes (AR, AP, GL, ACH, Positive Pay and multi-state tax) against the live AS400 baseline
  • Tracked and categorized 136 open configuration items

The result was an evidence-based picture of readiness, not a feature checklist. That is what the go/no-go call was made on.

The Outcome

A go-live decision backed by evidence.

A premature go-live was prevented. Five critical risk categories were caught before cutover: payment processing, routing, allocation override, EDI with SPS Commerce, and the E-Store. There was no ERP-driven disruption to order fulfillment through the facility relocation.

The readiness work also gave Paper Enterprises the most complete picture of its requirements it had ever documented. It supported a phased Odoo 19 plan, with multi-entity expansion, at about 34% lower five-year TCO than continuing on PBS. That Odoo work is now in flight.

Verified Review
★★★★★
"The personnel assigned to our project had broad and in depth knowledge of systems."
John Strass · Controller, Paper Enterprises Inc. · Distribution
5.0 · Verified on Clutch · Oct 6, 2026 →
Ready to reimagine how your operation runs?
Tell us what's holding you back, and we'll show you what it's costing you and fix it.